Annual Report 2015 47

FY2015 Production

A total of 485,302t of ore was mined during FY2015 from the Bentley underground mine.

A total of 488,466t of ore at an average grade of 10.55% Zn, 1.75% Cu and 156g/t Ag (FY2014: 441,867t @ 10.65% Zn, 1.97% Cu

and 145g/t Ag) was milled. Metal production in concentrate was 45,000t of contained zinc metal (FY2014: 41,162), 7,380t of

contained copper metal (FY2014: 7,692t) and 1,876,381oz of contained silver metal (FY2014: 1,657,461oz). Production of both zinc

and copper was in line with improved FY2015 guidance released in February 2015. The payable cash costs plus royalties was

$0.43/Ib payable zinc, net of by-product (FY2014: $0.31/Ib).

Figure 16: Quarterly mine production and cash cost performance at Jaguar in last eight quarters

Zinc (t)

Contained Metal (t)

Cash Costs ($/lb Zn)

Copper (t)

Zinc Guidance

Cash Costs ($/lb Zn)

Cost Guidance

Copper Guidance

Sep 13 Dec 13 Mar 14 Jun 14 Sep 14 Dec 14 Mar 15 Jun 15

18,000

16,000

14,000

12,000

10,000

8,000

6,000

4,000

2,000

-

$0.90

$0.80

$0.70

$0.60

$0.50

$0.40

$0.30

$0.20

$0.10

Figure 17: Quarterly tonnes mined versus Reserve depletion at Jaguar in last eight quarters

Sep 13 Dec 13 Mar 14 Jun 14 Sep 14 Dec 14 Mar 15 Jun 15

Ore tonnes

140,000

120,000

100,000

80,000

60,000

40,000

20,000

0

Mined

Reserve Depletion