Gas Pipeline Project

In July 2014, AngloGold Ashanti, on behalf of the joint venture partners, entered into agreements with APA Group (APA) for the

transportation of natural gas to the TGM. Under the agreements APA will construct a new 292km gas pipeline which will connect

TGM to APA’s Goldfields Gas Pipeline and Murrin Murrin lateral. Construction of the 292km long gas pipeline remains on target to

be completed by the end of 2015 with first delivery of gas to Tropicana scheduled for early 2016.

June 2014 A$1,249/oz Au

Open Cut Reserve Pit Design

June 2014 A$1,500/oz Au

Mineral Resource Pit Shell

HAVANA OPEN PIT

TROPICANA OPEN PIT

BOSTON SHAKER

OPEN PIT

Havana Deeps

Underground

Target

Open

Open

Open

Open

HAVANA SOUTH

OPEN PIT

Open

Image source:

Figure 7: Tropicana Gold Mine – Boston Shaker, Tropicana, Havana and Havana South open pit outlines

AS PART OF A CONCEPTUAL MINING STUDY, THE JOINT

VENTURE PARTNERS ARE EVALUATING THE DEPTH AND STRIKE

EXTENSIONS OF

THE TROPICANA MINERALISED SYSTEM

.